Hills M2 Integration
Find out more

Overview

Construction of the NorthConnex tunnel involves modifications to the Hills M2 Motorway west of Pennant Hills Road. These modifications will enable southbound traffic from the NorthConnex tunnel to merge safely with westbound traffic on the motorway. To facilitate work, the following changes are in place on the Hills M2 Motorway:

- two westbound lanes are operating between Pennant Hills Road and Windsor Road, with buses using the general traffic lanes;

- a reduced speed limit of 80km per hour in this section of the M2;
- temporary night time reduced speed limits and lane closures both west and eastbound may be in place;

- cycle access has been temporarily removed from the Hills M2 between Pennant Hills Road and Windsor Road and a detour has been provided.

Temporary construction facilities are required to support the integration work, including bridge work and lane widening on the westbound side of the Hills M2 Motorway.

All these construction facilities will be removed, landscaped and/or rehabilitated when the Hills M2 Motorway integration works are complete.

Third lane opens to traffic

A third westbound lane between Pennant Hills Road and Windsor Road on the Hills M2 Motorway has opened three months ahead of schedule, resulting in a safer and more efficient journeys for motorists.

Transurban Group General Manager for NSW, Kris Cooney, said accelerating this opening highlights Transurban’s commitment to easing congestion and improving traffic flow on one of Sydney’s busiest motorways.

“Fast tracking the opening of this westbound lane demonstrates our commitment to work hard at continually improving the journey of our Hills M2 customers.”

Read more here.

Project Status

Construction updates